How I lead product delivery

Sector
UK EV charging software
Period
2025 to 2026
Role
Product Delivery Lead, then Head of Product and Strategic Delivery
01

Problem

When I took over delivery, a small, distributed product and engineering team was shipping with no release gates, and it wasn't clear who decided what. Unfinished work reached commercial teams as if it were ready, and scope kept growing late in a release.

02

What was mine

I led delivery, then built and led the product team. I wrote the release gate and the rule that keeps early walkthroughs apart from live demos, led the daily technical standups and wrote the map of who decides what. Engineering built every release, and I decided what went into each one and when.

03

Actions

This is how I run delivery.

  • I set a short written gate that every release passes before regression testing.
  • I walk commercial colleagues through work in progress, and keep live demos until after regression.
  • I write down who decides what.
  • I lead a daily technical standup.
  • I start on Kanban and move to Scrum once things settle. On my team that took eight weeks.
  • I hold scope once it's agreed.
04

Decisions and trade offs

Showing work early gets commercial feedback sooner. It also means something still in testing can be shown, or promised, as finished. So I kept the two apart.

Holding scope meant telling people a reasonable request had to wait for the next release. I chose that over a late release.

Later I trialled sprints planned around releases.

05

Outcome

Delivery ran this way for as long as I led it. Revenue from product adoption more than doubled in 18 months.

06

What I learned

I learned to keep the release gate short enough to get through on a busy release day.

07

See it working

Every Lab demo carries its PRD: the problem, the success measures, the rollout gates and the decision record behind what I built.